Last week it became clear that Stegra, previously known as H2 Green Steel, will receive an additional contribution from taxpayers of almost 400 million SEK. Now the Sweden Democrats are raging against the million-rolling.

In October, it was reported that Stegra’s production start has been further delayed and is now scheduled for the beginning of 2027. According to the company, the rising costs are due to increased construction costs, lack of state support, and new infrastructure projects.

Last week, the Swedish Energy Agency announced that it will provide 390 million SEK in support to Stegra. The decision refers to the project’s